Waterline Replacement – Phase 2 Progress Update (August 2025)

The Rayford Road Municipal Utility District (MUD) is making significant progress on phase 2 of the waterline replacement project. As of today, August 5, 2025, construction continues on Pincher Creek Dr and Nanton Dr.

Upcoming Construction Areas

Once the work on Pincher Creek and Nanton is complete, the project will transition to the following areas:

  • Granum Drive
  • Mercoal Drive
  • Medway Drive
  • Falher Drive

Specific Work Addresses

The waterline replacement will directly affect the following addresses within the work area:

  • 30103-30115 Granum Drive
  • 1602-1715 Mercoal Drive
  • 30103-30122 Falher Drive
  • 1602-1735 Medway Drive

Residents in these areas can expect temporary construction-related impacts, including noise, road closures, and potential interruptions to water service. The MUD will strive to minimize inconveniences and provide advance notice of any service disruptions.

Thank you for your patience and cooperation as we work to improve the community’s water infrastructure. Together, we’re building a better future for all residents of Rayford Road MUD!

Rayford Road MUD Water Line Rehabilitation: Phase Two Begins June 16

As part of our ongoing commitment to delivering excellent service to residents, Rayford Road MUD is rehabilitating water lines that have been in service for over 45 years. This important infrastructure work is being completed in phases. Phase one is nearing completion, and phase two is scheduled to begin on June 16, 2025.

The streets impacted by this work are:

  • Imperial Oaks Blvd
  • Medway Drive
  • Mercoal Drive
  • Pincher Creek Drive
  • Wickburn Drive
  • Rycroft Drive
  • Whitelaw Drive
  • Havenhouse Drive
  • Stoney Plain Drive
  • Bashaw Drive
  • Falher Drive
  • Lauri Lynn Drive
  • Nanton Drive
  • Little Croft Street
  • Calmar Drive
  • Granum Drive

Construction will occur within the street right of way and may result in brief periods without water. If you have any concerns regarding the construction, please contact the District Engineer, Jason Hajduk, at 832-590-7148.

Winter Weather Update from Best Trash

With the latest snow forecast for Tuesday, Best Trash will be closed for regular operations tomorrow.

Please see the revised schedule below for the tentative schedule for the rest of the week.

  • Monday: We will run a regular service day.
  • Tuesday: Closed.
  • Wednesday: Delayed start.
  • Thursday: Delayed start.

Note: If the landfills close due to inclement weather, we cannot run our routes on those day(s).

The guidelines are subject to change depending on the actual weather conditions.

If we are unable to run our routes on your scheduled service day, your pick-up will be on the next scheduled service day.

If plants die due to the weather, they will be considered storm debris and handled accordingly.

Best wishes, and be safe.

Rayford Road MUD Waterline Replacement Project Update: January 7, 2025

The Rayford Road Municipal Utility District (MUD) is making significant progress on the waterline replacement project. As of today, January 7, 2025, construction continues within Imperial Oaks Boulevard.

Upcoming Construction Areas

Once the work on Imperial Oaks Boulevard is complete, the project will transition to the following areas:

  • Medway Drive
  • Thorsby Drive
  • Mercoal Drive

Specific Work Addresses

The waterline replacement will directly affect the following addresses within the work area:

  • 2002-2130 Medway Drive
  • 30102-30118 Thorsby Drive
  • 2002-2127 Mercoal Drive

Residents in these areas can expect temporary construction-related impacts, including noise, road closures, and potential interruptions to water service. The MUD will strive to minimize inconveniences and provide advance notice of any service disruptions.