Update on Phase 2 Waterline Replacement Project – March 16, 2026

The Rayford Road Municipal Utility District (MUD) is continuing to make significant progress on phase 2 of the waterline replacement project. As of today, March 16, 2026, the main line installation is complete, and crews are continuing to work on new service taps and restoring disturbed areas.

Upcoming Construction Areas

The project will transition to the following areas to complete site restoration and install new service taps:

  • Havenhouse Drive
  • Whitelaw Drive
  • Nanton Drive
  • Rycroft Drive

Specific Work Addresses

The waterline replacement will directly affect the following addresses within the work area:

  • 1907-1943 Havenhouse Drive
  • 1903-1923 Whitelaw Drive
  • 30202-30315 Nanton Drive
  • 1902-1927 Nanton Drive

Residents in these areas can expect temporary construction-related impacts, including noise, road closures, and potential interruptions to water service. The MUD will strive to minimize inconveniences and provide advance notice of any service disruptions.

Thank you for your patience and cooperation as we work to improve the community’s water infrastructure. Together, we’re building a better future for all residents of Rayford Road MUD!

Waterline Replacement – Phase 2 Progress Update (December 2025)

The Rayford Road Municipal Utility District (MUD) is continuing to make significant progress on phase 2 of the waterline replacement project. As of today, December 17, 2025, the main line installation is expected to be completed this week.

Upcoming Construction Areas

Once the main line installation is complete, the project will transition to the following areas to complete site restoration and install new service taps:

  • Pincher Creek Drive
  • Bashaw Drive
  • Calmar Drive
  • Nanton Drive

Specific Work Addresses

The waterline replacement will directly affect the following addresses within the work area:

  • 1603-1939 Pincher Creek Drive
  • 30003-30123 Bashaw Drive
  • 1602-1734 Calmar Drive
  • 30002-30131 Nanton Drive

Residents in these areas can expect temporary construction-related impacts, including noise, road closures, and potential interruptions to water service. The MUD will strive to minimize inconveniences and provide advance notice of any service disruptions.

Thank you for your patience and cooperation as we work to improve the community’s water infrastructure. Together, we’re building a better future for all residents of Rayford Road MUD!

🗑️ Holiday Trash & Recycling Schedule Update from Best Trash

🎁 Season’s Greetings!
Best Trash wishes everyone a joyful and safe holiday season — thank you for allowing us to be a part of the community!

🚫 No Collection Dates

Applies ONLY to customers with:

  • Trash collection on Monday & Thursday
  • Recycle collection on Thursday


♻️ Extra Recycling Tip

Overflow recycling may be placed in:

  • Clear bags
  • Cardboard boxes clearly marked “Recycle”

⏰ Important Reminders for all Customers!

  • Place bins at the curb by 7:00 AM on your scheduled day.
  • Pickup may be earlier than usual (lighter volume).
  • Or delayed due to increased holiday waste.

🙏 Thank you for your cooperation as our crews work hard to keep everything running smoothly!